Construction Update: Return of the One57 Crane
The One57 crane has finally returned to the top of the tower, and completion of the residential supertall is now imminent. Work was almost finished on the tower when the crane became one of Hurricane…
The One57 crane has finally returned to the top of the tower, and completion of the residential supertall is now imminent. Work was almost finished on the tower when the crane became one of Hurricane…
400 Park Avenue South is finally going vertical, and the tower is now at its second floor. The Portzamparc-designed building—to have both condominiums and rental apartments—will eventually reach 476 feet in height. The below photos…
432 Park is now growing consistently, rising one floor every six day—the tower’s impact on the streetscape has increased noticeably since the last update. Accounting for the double floors, the core is up to the…
Though the One57 saga continues—glass has made no recent progress—the new crane is finally being installed, with the turntable for the ‘cab’ now visible. Nearly six months have passed since Hurricane Sandy, and the logistics…
Progress continues at 150 Greenwich, which should be the first of the new World Trade Center towers to open. Glass has reached the top of the building on three out of four sides, and exterior…