Stalled 45 Park Place Skyscraper Enters Seventh Unfinished in Tribeca, Manhattan

45 Park Place. Rendering by Williams New York

The second building on our Turkey Week rundown of stalled projects in New York City is 45 Park Place, a 43-story residential skyscraper in Tribeca, Manhattan. Designed by SOMA Architects and Ismael Leyva Architects and developed by Sharif el-Gamal of Soho Properties, the 667-foot-tall structure was planned to yield 50 condominium units. The property is located between Church Street and West Broadway.

Much like Seaport Residences, 45 Park Place has stood unfinished in the same condition since the start of the decade. The glass curtain wall encloses only the bottom half of the reinforced concrete superstructure, and the tower crane remains anchored to the western elevation despite not being used since 2019. Unlike Seaport Residences, however, the project’s troubles are only financial in nature, and a possibility remains that the skyscraper could one day be finished.

45 Park Place. Photo by Michael Young.

45 Park Place. Photo by Michael Young.

45 Park Place. Photo by Michael Young.

45 Park Place. Photo by Michael Young.

45 Park Place (right) seen from Brooklyn. Photo by Michael Young

45 Park Place. Photo by Michael Young

45 Park Place. Photo by Michael Young

The project’s financial troubles became apparent in April 2019, when Domani Inspection filed for an unpaid sum of nearly $50,000 from el-Gamal. At that time, the developer was seeking an additional $200 million condo inventory loan on top of the project’s original $219 million loan. The developer had projected a condominium sellout of $450 million, but only 11 of the 50 units were sold by April 2019. The remaining 39 homes were taken off the market later that year.

The following year, just before the city shut down from the pandemic, the lending team of Malayan Banking Berhad, Intesa Sanpaolo S.P.A., WARBA Bank K.S.C.P., MSD Capital, and the Saudi Arabian Al Subeaei family initiated a foreclosure against the project’s Park Place Development LLC after it defaulted on the $219 million loan.

Then in January 2021, general contractor Gilbane Residential Construction filed a suit over more than $15 million in debts. By July, subcontractors Permasteelisa North America, Construction Realty Safety Group, and Domani Inspection Services led a petition to bring the developer into involuntary Chapter 7 bankruptcy for more than $25 million in unpaid work performed in 2019 and 2020. The lenders have also sought foreclosure over at least $117 million in defaulted debts. This July, The Real Deal reported on an additional set of lawsuits between the contractors and lenders.

The project’s fortunes could be changing soon, however. This September, Crain’s New York reported that the project was headed to a foreclosure auction, though no public record of the proceedings is available.

Subscribe to YIMBY’s daily e-mail

Make YIMBY preferred on Google

Follow YIMBYgram for real-time photo updates
Like YIMBY on Facebook
Follow YIMBY’s Twitter for the latest in YIMBYnews

.

Be the first to comment on "Stalled 45 Park Place Skyscraper Enters Seventh Unfinished in Tribeca, Manhattan"

Leave a comment

Your email address will not be published.


*